Greek draft law would make data centres post €200,000 per MW, source 60% renewables and pay their full grid costs
The rules sat in articles 19 to 28 and 55 of the consultation text of Greece's electricity-market bill, which was tabled in Parliament on 31 October 2026 with an annual fee of €15,000 per MW added; it is not yet law.
19We read 19 sources, all in Greek, 4 of them official documents, including articles 19 to 28 and the transitional article 55 of the consultation text on opengov.gr, and article 27 of the bill tabled in Parliament, so you can read this in 9 minutes. What we checked ↓
Does this affect you?
- Data-centre developers with a pending connection request
- Within 12 months of the law's publication, and before a final connection offer is granted, you would have to file the new application documents, including the €200,000-per-MW guarantee; requests above 10 MW pending at ΔΕΔΔΗΕ would move to ΑΔΜΗΕ and be ranked by the date their file is complete under the new rules.1
- Holders of a final connection offer without a connection contract
- Within five months of the law's publication, and in any case before signing the connection contract, you would have to file the new documents, an electricity purchase agreement meeting the 60% renewables rule and a technical report, or the offer is cancelled.1
- Data centres that have already signed a connection contract
- The same five-month deadline would apply; if you miss it, the offer and the connection contract would cease to be valid automatically.1
- Data-centre operators
- Under article 27 of the tabled bill, you would pay an annual special fee of €15,000 per MW of maximum consumption capacity, for household consumers and the municipalities of the area where your data centre is sited.13
- Households and other electricity customers
- The cost of grid works needed solely to connect a data centre would fall entirely on its owner and would not enter the regulated asset base (the network assets whose cost the operators recover through charges on all consumers) of ΔΕΔΔΗΕ or ΑΔΜΗΕ.1
What to do Nothing changes yet: the bill was tabled in Parliament on 31 October 2026 and is not law, and the five-month and 12-month clocks would start only when it is published in the Government Gazette.121 Its committee reading starts on Tuesday, 3 November 2026 by our calculation; no plenary date had been announced by 1 November 2026.16
Where it stands
Checked 1 November 2026- Bill published for public consultation on opengov.gr110 Oct 2026
- Public consultation closed at 10:001724 Oct 2026
- Tabled in Parliament and sent to the Standing Committee on Production and Trade121331 Oct 2026
- Standing Committee on Production and Trade begins its reading163 Nov 2026 · next
- Voted in Parliament and published in the Government Gazette (ΦΕΚ): five-month and 12-month deadlines for projects already in the queue start81No plenary date announced as of 1 November 2026; the minister's aim was the first week of November (Insider, 26 October)
- Implementing decisions: renewables methodology, Data Centre Register and saturation list1Not scheduled
At a glance
- Tabled, not law: Greece's electricity-market bill, sent to Parliament on 31 October 2026, would require a letter of guarantee (from a bank or insurer) of €200,000 per MW of a data centre's maximum consumption capacity, cut by 25% when the connection contract is signed. Article 27 of the tabled bill adds an annual fee of €15,000 per MW for household consumers and the host municipalities.
- Data centres would have to cover at least 60% of their annual electricity use from renewables from their first day of operation, and would pay the full actual cost of their grid connection, including their share of the upstream grid they use.
- Projects that already hold a final connection offer or a signed connection contract would have five months from the law's publication to file the new documents, an electricity purchase agreement and a technical report, or lose the offer and any contract (article 55 of the consultation text; we have not checked the tabled version).
Greece's electricity-market bill contains a dedicated chapter of rules for connecting data centres to the grid.1 In the consultation text that ΥΠΕΝ (Υπουργείο Περιβάλλοντος και Ενέργειας, Ypourgeio Perivallontos kai Energeias), the environment and energy ministry, put out on 10 October 2026, the rules sat in articles 19 to 28.1 It is the same bill that would cut the PSO charge on household electricity bills.12 The public consultation closed on 24 October 2026.17 The bill was tabled in Parliament on Saturday 31 October 2026, and nothing in it is law yet.121415 It goes to the Standing Committee on Production and Trade on Tuesday, the state news agency ΑΠΕ-ΜΠΕ reported; by our calculation, that is 3 November 2026.16 Insider reported on 26 October 2026 that the environment and energy minister, Stavros Papastavrou (Σταύρος Παπασταύρου), aimed for a vote in the first week of November; that is an aim, not a parliamentary timetable.8
The bill would require a letter of guarantee per megawatt, a 60% renewables share from day one and full payment for the grid works each data centre needs.1 Its transitional article (article 55 in the consultation text) would also reach projects already in the queue, with deadlines that start on the day the law is published in the ΦΕΚ (Φύλλο Εφημερίδας της Κυβερνήσεως, Fyllo Efimeridas tis Kyverniseos), the Government Gazette.1
Article numbers below are those of the consultation text unless we say they belong to the tabled bill.1 In the tabled bill, article 27 is still a data-centre article and article 29 is still the home-solar article, as in the consultation text; we have not checked the numbering of the other data-centre articles.13
What changed in the tabled bill?
Article 27 of the tabled bill sets an annual special fee for data centres of €15,000 per MW of maximum consumption capacity.13 The fee goes to household consumers and to the first-tier local authorities (Οργανισμοί Τοπικής Αυτοδιοίκησης Α' βαθμού, Organismoi Topikis Aftodioikisis A' vathmou, that is, the municipalities) of the areas where the data centres are sited.13 It is to be shared out and paid to them by applying article 87 of law 4964/2022 by analogy.13 By our calculation, the fee would come to €1.5 million a year for a 100 MW data centre and €4.5 million a year for a 300 MW one. Energymag, a specialist energy news site, reported on 31 October 2026 that the fee was one of the changes made after the consultation.17
Energymag also reported three other changes, which we have not checked against the tabled text:17
- New renewables only: the 60% share would have to come from new renewable plants that hold a final connection offer, and those renewable and storage plants would have to be operating by the time the data centre is energised; otherwise energisation is suspended, Energymag reported.17
- No operating aid: the tabled text rules out operating aid for the renewable and storage capacity that supplies data centres, according to Energymag.17
- Flexible connections: in a wider grid-connection rule, the tabled text drops the consultation draft's power for the minister to set how compensation for flexible connections is calculated; Energymag said the right to compensation itself remains in article 15.17
The ministry's release on the tabling repeats the headline points: investors bear the full cost of connection and of the necessary grid reinforcement works, data centres cover at least 60% of annual consumption from renewables, and they post a €200,000-per-MW letter of guarantee.1415 On 29 October 2026, before the bill was tabled, Insider and Michanikos Online reported, citing unnamed sources at or close to the ministry, that the final data-centre provisions would change only in limited ways.1819
Who handles a data centre's request?
Data centres of up to 10 MW of maximum consumption capacity would apply to ΔΕΔΔΗΕ (Διαχειριστής του Ελληνικού Δικτύου Διανομής Ηλεκτρικής Ενέργειας, Diacheiristis tou Ellinikou Diktyou Dianomis Ilektrikis Energeias), the distribution-network operator.1 Larger ones would apply to ΑΔΜΗΕ (Ανεξάρτητος Διαχειριστής Μεταφοράς Ηλεκτρικής Ενέργειας, Anexartitos Diacheiristis Metaforas Ilektrikis Energeias), the high-voltage transmission operator.1 From 4 MW, a request that ΔΕΔΔΗΕ cannot connect for technical reasons would pass to ΑΔΜΗΕ and keep its original filing date.1 Splitting one functional unit (λειτουργική ενότητα: the same facility on the same or adjacent plots, requested within a year by the same or linked companies) into smaller requests would not be allowed.1
No request could be filed without first entering the site in a new electronic Data Centre Register kept by ΡΑΑΕΥ (Ρυθμιστική Αρχή Αποβλήτων, Ενέργειας και Υδάτων, Rythmistiki Archi Apovliton, Energeias kai Ydaton), the regulatory authority for waste, energy and water.1
How much would the guarantee cost?
Every application would need a letter of guarantee («εγγυητική επιστολή»), issued by a bank or an insurer, of €200,000 per MW of maximum consumption capacity.1 The guarantee would have to run for at least three years, fall by 25% of its original value when the connection contract is signed, and fall further, pro rata, as the site is energised in stages.1 By our calculation, a 100 MW data centre would post €20 million, falling to €15 million after the 25% cut. By our calculation, a 300 MW project would post €60 million, falling to €45 million. Mikrometoxos said the guarantee for a 300 MW investment, such as the first phase of the plan by PPC (ΔΕΗ, Δημόσια Επιχείρηση Ηλεκτρισμού, Dimosia Epicheirisi Ilektrismou) and Amazon Web Services in Western Macedonia, "could reach" €60 million, in our translation.5 The bill names no projects, and whether and when that project would have to post it depends on the stage its grid request has reached; OT.gr and To Vima reported in September 2026 that a grid-connection application had been submitted for the data centre at the Agios Dimitrios power station site, but not whether an offer has been granted.1910
The guarantee would be forfeited if it is not renewed, if the site is not fully energised while the offer (or its extension) is valid, or if the applicant withdraws after receiving the final connection offer («Οριστική Προσφορά Σύνδεσης», Oristiki Prosfora Syndesis: the operator's formal offer of a grid connection and its terms).1 The forfeited money would go to a sub-account of the special account that funds renewables support.1 A connection offer would last three years if accepted within two months, and could be extended once, for up to two years, together with its reservation of grid capacity («δέσμευση ηλεκτρικού χώρου»), for a fee of €2,000 per MW per month.1 By our calculation, that is €600,000 a month for a 300 MW project, or €14.4 million for a full two-year extension.
Applicants connecting to the transmission grid would also need annual turnover (counting shareholders and linked companies) above 30% of the project's construction cost, reckoned at €10 million per MW, in at least one of the last three years.1 By our calculation, that means more than €300 million of turnover for a 100 MW project. Other requirements include a full environmental impact study file, a lease or concession of the site for at least ten years and a €250 application fee.1
What does the 60% renewables rule require?
From the start of operation, data centres would have to cover at least 60% of their total annual electricity consumption from renewable plants.1 They could do so through a direct connection to renewable plants and storage, through bilateral agreements settled financially (financial PPAs), or through physical delivery from renewable producers.1 Self-consumption with time-matched netting (ταυτοχρονισμένος συμψηφισμός, where a plant's output offsets consumption only in the same time interval) could also count.1 Compliance would be judged on the renewable and storage plants' actual output against the data centre's actual consumption over the same period, using a method to be set by a later decision (under article 51(7) of the law being amended, 4951/2022).1 That decision has not yet been issued, The Total Business noted on 12 October 2026.6 Article 27 of the consultation text does not mention guarantees of origin.1 Energymag reports that the tabled text requires the 60% to come from new renewable plants; we have not checked that.17
Which data centres would get priority?
Requests above 200 MW would be assessed with "absolute priority", in our translation, over other requests.1 To qualify, the holder would have to file a formal declaration (υπεύθυνη δήλωση) that at least 80% of the data centre's maximum consumption capacity will be covered by a dispatchable plant and/or storage able to supply at least six hours at that maximum, commissioned after 1 January 2027 and no later than the data centre itself.1
Insider reported on 12 October 2026 that data-centre requests to ΑΔΜΗΕ had reached 9 GW, plus at least 220 MW on the distribution network.3 Newsit reported a jump from 5 GW to 9 GW within a few months of 2026.4 Neither outlet gave an official source for the figure.34
Who pays for the grid?
Every two months, ΑΔΜΗΕ would class its existing extra-high-voltage centres (Κέντρα Υπερυψηλής Τάσης, Kentra Yperypsilis Tasis, or Κ.Υ.Τ.: the large substations where the transmission grid steps down) as saturated, partly saturated (less than 50% spare capacity) or not saturated, and ΡΑΑΕΥ would publish the list.1 A saturated substation could mean no offer, an offer elsewhere, or an obligation to build a new substation.1 Even at an unsaturated substation, the investor would pay the full actual cost of connection, including its share of the existing or new upstream infrastructure it uses.1 Grid works needed solely for a data centre would fall "entirely" on its owner and stay out of the operators' regulated asset base, in our translation.1 The ministry's announcement, as republished by e-nomothesia, described this as investors bearing the full cost of connection and of the necessary reinforcement works.2
What happens to projects already in the queue?
Under article 55 of the consultation text, pending requests would have to file the new documents, including the guarantee, within 12 months of the law's publication and before a final connection offer is granted.1 Requests above 10 MW pending at ΔΕΔΔΗΕ would move to ΑΔΜΗΕ and be ranked by the date their file is complete under the new rules.1 Holders of a final connection offer without a contract would have five months (and in any case until they sign a connection contract) to file them, plus an electricity purchase agreement meeting the 60% rule and a technical report, or the offer is cancelled.1 The same five months would apply to projects that have already signed a connection contract.1 We have not checked whether the tabled bill changed these deadlines or the number of the article that sets them.13
Under article 55, paragraph 6 of the consultation text, a data centre that has signed a connection contract but misses the five-month deadline would lose both its offer and its contract automatically.1 Article 55 sets a deadline for each stage a project may have reached, but it does not name projects, so it does not say which deadline would apply to the PPC–AWS data centre in Kozani.1 Responding to the bill, the Greek association of data-centre builders and operators (Ελληνική Ένωση Κατασκευαστών και Λειτουργών Κέντρων Δεδομένων, GRDCA) asked for existing offers and contracts to be kept on their original terms, saying the holders of those projects have already made commitments to builders, financiers and customers, according to Naftemporiki on 26 October 2026 (in our translation).11
What happens next?
The bill goes to Parliament's Standing Committee on Production and Trade (Διαρκής Επιτροπή Παραγωγής και Εμπορίου, Diarkis Epitropi Paragogis kai Emporiou), which starts work on it on Tuesday, 3 November 2026 by our calculation.1216 We found no plenary vote date as of 1 November 2026.1216 Once the law is published in the ΦΕΚ, the five-month and 12-month deadlines for projects already in the queue would start to run.1
Follow this story
We update this article when it moves: the tracker above shows where it stands. To keep up: add the key dates to your calendar, follow our updates feed or get the daily brief. All bills we follow are on one page.
What we checked
Highlights from our fact-check against the original Greek documents. Every claim in the article went through the same check.
- Not in the document
Data-centre requests to ΑΔΜΗΕ have reached 9 GW, plus at least 220 MW on the distribution network, Insider reported; Newsit put the jump at 5 GW to 9 GW in a few months.34
The data-centre articles (19 to 28) and transitional article 55 of the consultation text give no figure for the queue, and neither outlet cites an official source for it. We treat 9 GW as reported, not official.1
- Confirmed
Data centres would post a guarantee of €200,000 per MW, cut by 25% when the connection contract is signed, Mikrometoxos reported.5
Article 23 of the consultation text sets the letter of guarantee at €200,000 per MW of maximum consumption capacity and cuts it by 25% of its original value when the connection contract is signed, then pro rata as the site is energised in stages.1
- Confirmed
Projects already holding a connection offer or contract would have five months to file the new documents, «αλλιώς τη χάνουν» (or they lose it), The Total Business reported; the ministry's summary of the bill did not mention projects already in the queue.62
Article 55 of the consultation text gives final-offer holders five months from the law's publication, or the offer is cancelled; for projects with a signed connection contract, the offer and the contract cease to be valid automatically. Pending requests get 12 months.1
- Confirmed
Data centres must cover at least 60% of their annual electricity consumption from renewables, the ministry's announcement said.2
Article 27 of the consultation text requires at least 60% of total annual consumption from renewable plants from the start of operation, but leaves the measurement method to a later decision that, The Total Business notes, has not been issued.16
- Confirmed
The tabled bill sets an annual special fee of €15,000 per MW of maximum consumption capacity for data centres, for household consumers and the host municipalities, Energymag reported.17
Article 27 of the tabled bill sets the fee at €15,000 a year per MW of maximum consumption capacity, for household consumers and the first-tier local authorities of the areas where data centres are sited.13
What we don't know yet
- Whether the PPC–AWS project in Kozani holds a final connection offer or a signed connection contract. OT.gr and To Vima reported in September that a grid-connection application had been submitted [S9][S10]; neither said an offer had been granted, so which transitional deadline would apply is still unknown.
- How the 60% renewables share will be measured (annual, monthly or hourly matching): the bill leaves the method to a later decision that has not been issued.
- Whether guarantees of origin can count towards the 60%: article 27 of the consultation text, which sets the 60% rule, does not mention them. If Energymag's report that the 60% must come from new renewable plants is confirmed [S17], that would narrow the question.
- The official size of the data-centre queue: the 9 GW figure comes from press reports that cite no source; we found no figure from ΑΔΜΗΕ or the ministry.
- When the bill will be voted in plenary: its committee reading starts on Tuesday 3 November 2026, by our calculation, and no plenary date had been announced by 1 November [S16]. Also whether the tabled text kept the transitional deadlines that the data-centre association GRDCA asked to soften [S11].
- Whether the tabled text contains the 'new renewables only' rule, the exclusion of operating aid and the change to flexible-connection compensation as Energymag described them, and whether these rules and the €15,000-per-MW fee apply to projects already in the queue [S17].
- Which article numbers the other data-centre rules (the guarantee, connection costs and transitional deadlines) carry in the tabled bill: we have checked only article 27.
- Whether the ministry has published a report on the consultation showing how it answered the comments on the data-centre articles: it is not among the separate files tabled with the bill, though it may be part of the regulatory impact analysis, which we have not read [S12].
- When ΡΑΑΕΥ will set up the Data Centre Register and publish the first list of saturated substations.
«Το ύψος της εγγυητικής επιστολής της παρ. 1 καθορίζεται σε διακόσιες χιλιάδες (200.000) ευρώ ανά μεγαβάτ (ΜW) μέγιστης ισχύος κατανάλωσης»
The amount of the letter of guarantee of par. 1 is set at two hundred thousand (200,000) euros per megawatt (MW) of maximum consumption capacity (in our translation)
«Με την επιφύλαξη της απόφασης της παρ. 7 του άρθρου 51, τα Κέντρα Δεδομένων από την έναρξη της λειτουργίας τους καλύπτουν τουλάχιστον το εξήντα τοις εκατό (60%) της συνολικής ετήσιας κατανάλωσης ηλεκτρικής ενέργειάς τους από ηλεκτρική ενέργεια που παράγεται από σταθμούς Ανανεώσιμων Πηγών Ενέργειας»
Subject to the decision of par. 7 of article 51, Data Centres, from the start of their operation, shall cover at least sixty per cent (60%) of their total annual electricity consumption with electricity produced by Renewable Energy Sources plants (in our translation)
«Σε περίπτωση μη υποβολής των ανωτέρω εντός της τεθείσας προθεσμίας, η χορηγηθείσα Προσφορά Σύνδεσης και η σχετική Σύμβαση Σύνδεσης παύουν να ισχύουν αυτοδικαίως.»
If the above are not submitted within the set deadline, the Connection Offer granted and the related Connection Contract cease to be valid automatically (by operation of law). (in our translation)
«… [ειδικό τέλος υπέρ των οικιακών κα]ταναλωτών και των Οργανισμών Τοπικής Αυτοδιοίκησης Α’ βαθμού των περιοχών εγκατάστασής τους, το οποίο ανέρχεται σε ετήσια βάση σε δεκαπέντε χιλιάδες (15.000) ευρώ ανά μεγαβάτ (MW) μέγιστης ισχύος κατανάλωσης. Το ειδικό τέλος κατανέμεται και αποδίδεται στους δικαιούχους κατ’ αναλογική εφαρμογή του άρθρου 87 του ν. 4964/2022 (Α’ 150).»
… [a special fee in favour of household con]sumers and of the first-tier local authorities of the areas where they are installed, which amounts, on an annual basis, to fifteen thousand (15,000) euros per megawatt (MW) of maximum consumption capacity. The special fee is allocated and paid to the beneficiaries by analogous application of article 87 of law 4964/2022 (Α' 150). (in our translation)
Sources
- opengov.gr / Υπουργείο Περιβάλλοντος και Ενέργειας · Βελτίωση του σχεδιασμού της αγοράς ηλεκτρικής ενέργειας – Ενσωμάτωση της Οδηγίας (ΕΕ) 2024/1711 … και λοιπές διατάξεις (δημόσια διαβούλευση #1731) · 10 October 2026 · in Greek · Open ↗
Passage we quote: Consultation text, article 23 (new article 50Γ, paragraph 3, of law 4951/2022)
«Το ύψος της εγγυητικής επιστολής της παρ. 1 καθορίζεται σε διακόσιες χιλιάδες (200.000) ευρώ ανά μεγαβάτ (ΜW) μέγιστης ισχύος κατανάλωσης»
The amount of the letter of guarantee of par. 1 is set at two hundred thousand (200,000) euros per megawatt (MW) of maximum consumption capacity (in our translation)
Passage we quote: Consultation text, article 27 (new article 50Ζ, paragraph 1, of law 4951/2022)
«Με την επιφύλαξη της απόφασης της παρ. 7 του άρθρου 51, τα Κέντρα Δεδομένων από την έναρξη της λειτουργίας τους καλύπτουν τουλάχιστον το εξήντα τοις εκατό (60%) της συνολικής ετήσιας κατανάλωσης ηλεκτρικής ενέργειάς τους από ηλεκτρική ενέργεια που παράγεται από σταθμούς Ανανεώσιμων Πηγών Ενέργειας»
Subject to the decision of par. 7 of article 51, Data Centres, from the start of their operation, shall cover at least sixty per cent (60%) of their total annual electricity consumption with electricity produced by Renewable Energy Sources plants (in our translation)
Passage we quote: Consultation text, article 55, paragraph 6 (transitional provisions)
«Σε περίπτωση μη υποβολής των ανωτέρω εντός της τεθείσας προθεσμίας, η χορηγηθείσα Προσφορά Σύνδεσης και η σχετική Σύμβαση Σύνδεσης παύουν να ισχύουν αυτοδικαίως.»
If the above are not submitted within the set deadline, the Connection Offer granted and the related Connection Contract cease to be valid automatically (by operation of law). (in our translation)
- e-nomothesia.gr · Σε διαβούλευση νομοσχέδιο για την αγορά ηλεκτρικής ενέργειας, τη χωροταξία και το περιβάλλον · 11 October 2026 · in Greek · Open ↗ · Archived copy
- Insider.gr · Data centers: Ο οδικός χάρτης για τη σύνδεση στο δίκτυο - Οι υποχρεώσεις του επενδυτή · 12 October 2026 · in Greek · Open ↗ · Archived copy
- Newsit · Τάξη στην ολοένα και μεγαλύτερη «ουρά» των data center επιχειρεί να βάλει το ΥΠΕΝ · 12 October 2026 · in Greek · Open ↗ · Archived copy
- Mikrometoxos · Data centers: «Χρυσό εισιτήριο» για σύνδεση στο ρεύμα με εγγυήσεις εκατομμυρίων · 12 October 2026 · in Greek · Open ↗ · Archived copy
- The Total Business · Η Ελλάδα θέλει data centers. Αλλά όχι με τον λογαριασμό των καταναλωτών. · 12 October 2026 · in Greek · Open ↗ · Archived copy
- Michanikos Online · ΥΠΕΝ: Έληξε η διαβούλευση για το νέο ενεργειακό νομοσχέδιο – Οι αλλαγές σε ΑΠΕ, ηλεκτρικά δίκτυα, data centers και λογαριασμούς ρεύματος · 26 October 2026 · in Greek · Open ↗ · Archived copy
- Insider.gr · Ρεύμα: Οι «ενστάσεις» των προμηθευτών στο νομοσχέδιο του ΥΠΕΝ - Καλύτερη οριοθέτηση για την προστασία των καταναλωτών · 26 October 2026 · in Greek · Open ↗ · Archived copy
- Οικονομικός Ταχυδρόμος (OT.gr) · ΔΕΗ - Amazon: Η Κοζάνη στον χάρτη των data centers με αρχική ισχύ 300 MW και προοπτική 1 GW · 18 September 2026 · in Greek · Open ↗ · Archived copy
- Το Βήμα · ΔΕΗ: Τίτλοι τέλους για τoν ατμοηλεκτρικό σταθμό Κοζάνης - Από τοv λιγνίτη στο Data center · 22 September 2026 · in Greek · Open ↗ · Archived copy
- Ναυτεμπορική · "Ναι" με αστερίσκους για το νέο πλαίσιο των data centers · 26 October 2026 · in Greek · Open ↗ · Archived copy
- Βουλή των Ελλήνων (Hellenic Parliament) · Βελτίωση του σχεδιασμού της αγοράς ηλεκτρικής ενέργειας - Ενσωμάτωση της Οδηγίας (ΕΕ) 2024/1711 … και λοιπές διατάξεις (bill page: tabled 31 October 2026; Standing Committee on Production and Trade) · 31 October 2026 · in Greek · Open ↗
- Βουλή των Ελλήνων (Hellenic Parliament) · Σχέδιο νόμου: Βελτίωση του σχεδιασμού της αγοράς ηλεκτρικής ενέργειας - Ενσωμάτωση της Οδηγίας (ΕΕ) 2024/1711 … και λοιπές διατάξεις (tabled bill text, PDF, 129 pages) · 31 October 2026 · in Greek · Open ↗
Passage we quote: Tabled bill, article 27, end (page 38); OCR text from the Parliament PDF, checked by our editor; the words in square brackets were supplied by our editor where the extract begins mid-word
«… [ειδικό τέλος υπέρ των οικιακών κα]ταναλωτών και των Οργανισμών Τοπικής Αυτοδιοίκησης Α’ βαθμού των περιοχών εγκατάστασής τους, το οποίο ανέρχεται σε ετήσια βάση σε δεκαπέντε χιλιάδες (15.000) ευρώ ανά μεγαβάτ (MW) μέγιστης ισχύος κατανάλωσης. Το ειδικό τέλος κατανέμεται και αποδίδεται στους δικαιούχους κατ’ αναλογική εφαρμογή του άρθρου 87 του ν. 4964/2022 (Α’ 150).»
… [a special fee in favour of household con]sumers and of the first-tier local authorities of the areas where they are installed, which amounts, on an annual basis, to fifteen thousand (15,000) euros per megawatt (MW) of maximum consumption capacity. The special fee is allocated and paid to the beneficiaries by analogous application of article 87 of law 4964/2022 (Α' 150). (in our translation)
- Υπουργείο Περιβάλλοντος και Ενέργειας (ΥΠΕΝ) · Στη Βουλή το νομοσχέδιο του ΥΠΕΝ για μια πιο δίκαιη αγορά ηλεκτρικής ενέργειας, την προστασία των καταναλωτών και επενδύσεις 2,3 δισ. ευρώ στα νησιά · 31 October 2026 · in Greek · Open ↗
- Insider.gr · Στη Βουλή το ν/σ του ΥΠΕΝ για πιο δίκαιη αγορά ηλεκτρικής ενέργειας, προστασία των καταναλωτών και επενδύσεις 2,3 δισ. ευρώ στα νησιά (full copy of the ministry's release) · 31 October 2026 · in Greek · Open ↗ · Archived copy
- Capital.gr (ΑΠΕ-ΜΠΕ) · Βουλή: Κατατέθηκε το νομοσχέδιο του ΥΠΕΝ για τη βελτίωση του σχεδιασμού της αγοράς ηλεκτρικής ενέργειας · 31 October 2026 · in Greek · Open ↗ · Archived copy
- Energymag (Νίκος Φιλιππίδης) · Data centers με τέλος €15.000/MW και υποχρεωτικά με νέες ΑΠΕ – Όλες οι αλλαγές για αποθήκευση, αιολικά και βιοαέριο, αλλά και 49ετής παραχώρηση του Καραϊσκάκη στο ν/σ του ΥΠΕΝ μετά τη διαβούλευση · 31 October 2026 · in Greek · Open ↗ · Archived copy
- Insider.gr (Μιχάλης Μαστοράκης) · Τί απαντάει το ΥΠΕΝ για τα data centers – Περιορισμένες αλλαγές στις τελικές διατάξεις του νομοσχεδίου · 29 October 2026 · in Greek · Open ↗ · Archived copy
- Michanikos Online · Data Centers: Το ΥΠΕΝ διατηρεί αυστηρούς όρους σύνδεσης μετά τη διαβούλευση · 29 October 2026 · in Greek · Open ↗ · Archived copy
Every figure in the text links to its source. Our own calculations are marked as such. Translations from Greek are ours. Archived copies are snapshots saved on the Internet Archive when we published.